Assemble a consistent job snapshot

Choose a common reporting cutoff for the active jobs. A practical worksheet can include contract value, approved changes, costs recorded, estimated costs remaining and billings to date. Keep supporting job reports with the worksheet so the reviewer can see where each amount came from.

Review the estimate to finish with the field team

Ask the project manager what work, purchases and subcontractor commitments remain. Record changed assumptions and unresolved change orders separately. An updated cost-to-finish estimate helps explain why a job’s expected margin moved even when the contract value did not.

Compare progress with billing as a management exercise

As common bookkeeping practice, compare the progress assessment with amounts billed and identify jobs where billing appears ahead of or behind the work. Use those differences to prompt questions about billing timing, missing applications or revised estimates. This worksheet does not decide revenue recognition or tax treatment.

Use software detail to investigate the differences

Intuit describes phase filtering for Estimate vs. Actuals and WIP reports in QuickBooks Online Advanced with the Construction add-on and in Intuit Enterprise Suite. Where that feature is available, phase detail can help locate the work behind a changed estimate. Check the actual setup before relying on a report name.

Agree on the report’s purpose with the CPA

The IRS accounting-methods publication points readers elsewhere for long-term contract tax methods. Keep the management worksheet distinct from tax-method decisions and ask your CPA which adjustments belong in the financial statements. If a lender or surety requests a schedule, obtain its requested format instead of assuming a universal template.

Sources: WIP software and accounting context

Make job schedules easier to review

Tidwell organizes job costs and billing support for project review, working alongside your CPA on accounting decisions.

Explore construction reporting support
Call (805) 462-8608